|
|
Revival
Albatros website
Situation
Prior to Refurbishment Objectives
Refurbishment
Strategy Fabric improvements The
existing building was heated by gas furnace and had no insulation, single
glazed windows and inefficient artificial lighting. Refurbishing the existing
building envelope would have been prohibitively expensive. Therefore, a new,
second skin was installed over the existing façade. The steel construction
was replaced with an aluminium frame. The old façade was made air tight and
the openings replaced with airtight windows. The
second skin significantly improves the overall thermal quality of the façade
by preheating ventilation air and removing the existing thermal bridges.
Unwanted sound transmission to neighbouring offices through the air cavity
between the facades is minimised by installing noise absorbing material at
the ceiling of the cavity.
A
sun shading device was mounted in the cavity of the second skin. This is controlled automatically but has a
manual override. Lighting The
building is narrow with good day lighting and all desks are adjacent to
windows. Energy efficient lighting
with daylight dimmers and motion detectors were installed to reduce the electricity
demand for lighting. The Albatros second skin facade Heating and Cooling The
Albatros building is fortunately located adjacent to an existing CHP system.
The building was connected to this heat source through a district heating
system, in order to make use of waste heat from the CHP plant. The existing
convectors could not be re-used therefore new radiators were installed for
heating in the offices. In
summer, night ventilation is used to pre-cool the thermal mass of the
building. The uncovered, concrete ceilings enhance the exposed thermal mass,
contributing to comfortable indoor conditions. Ventilation A
good indoor climate has been achieved with passive measures. The building is
naturally ventilated with new and larger, openable windows and special
insulation behind the convector to avoid energy losses. Floor level
ventilation inlets and ceiling level ventilation outlets were created along
the full length of the façade; these are open in summer and closed in winter,
when simple vents are used. The Coanda effect is utilised, so fresh air
sticks to the ceiling panel where it mixes with room air before reaching
occupant level. Waste air is mechanically removed from the building, using
ducts and energy-efficient fans to decrease the use of electric energy. Innovative
Technologies
Completed
building
CO2 impact of the Albatros
refurbishment Commissioning During
construction, it was discovered that the specification did not show a
horizontal partition between floors in the second skin façade. This partition
was essential in reducing overheating by preventing warm air from lower
floors from rising to the higher floors. However, the partition was installed
before the construction work was finished. In
the commissioning period, it became apparent that there were problems with
the operation of the second skin façade. The ventilation grills were not
airtight and a mechanical defect meant that they did not close completely in
the winter period as designed, resulting in lower temperatures caused by the
extra ventilation in the second skin façade. In addition to this, the BEMS
controlling the operation of the grills was set up incorrectly. This caused
the building occupants to feel cold during the winter, and meant that there
was an unwanted noise in the façade when the high air flow moved along the
ventilation holes. To
reduce the number of complaints about the temperature, the night setback
mechanism was removed. The mechanical problems with the grills have now been
resolved and the BEMS adjusted to the correct settings. The supplier have
assured the WP 8 contractor that the air tightness meets design standards,
however this is still under question and there will be discussion on this
issue beyond the end of the REVIVAL project. It is intended that the night
setback will be introduced when the problem is resolved. Although
some minor problems occurred in the first months, the first experiences of
the users are good. Problems that occurred in the first month had all to do
with the double skin façade. During windy conditions there was a lot of noise
in the building. There were three causes for that problem. There were little
holes in open metal constructions. They work as an organ pipe when the air
strikes along the little holes. Closing the holes was the answer. The other
problem was that the big grills for summer ventilation didn’t close. That
problem is also fixed. The air in the double façade is much warmer now, and
the wind doesn’t have much effect on the pressure drop over the windows
between the offices and the double façade. Last problem was the air tightness
of the new open able windows. The construction firm will look after this
problem. |
|
Papers/presentations:
·
The REVIVAL national website
was launched in April 2005.
·
Glazenwassersbalkons benut
voor extra gavel, Article on the Albatros building published in the Dutch
journal for architects Bouwwereld, March 2004
·
Revival
of the Albatros, Thijs Kurstjens, Evert Vrins, Cees Leenaerts, Paper for the
Building Physics Conference PLEA September 2004
·
'REVIVAL'
van de Albatros, Paper published in the congress files from the Dutch National
Sustainable Building congress on 25 November 2005
·
Revival
of the Albatros, article in TVVL magazine, June 2006
·
Revival
of the Albatros, Full final report, W/E consultants 25 January 2008